Jack / Steve,
Thanks for your replies. I got your views & quite agree to your thoughts.
I
guess my Qn was incomplete, I would rephrase that:-
I have a programme of around 2000 activities & its got 20-30 odd
activities
for painting of walls and I need a "floating" Milestone up in the
Milestones
section to show when the painting of walls will start. The project is
currently at Foundation stage Walls will be erected according to a set
sequence. Can this be possible in MSP?
Apologies for not expaining it in the first go.
:
If there is no process-driven reason that the walls have to be painted in
a
certain order, don't link them to each other at all. Even if only you
have
only one painter so that only one wall can be worked at a time, that is a
resource availability issue, not a dependency linkage issue. Link
indicate
a required order, saying the schedule of the successor task MUST be
driven
by the scheduling of the predecessor. So set it up like this:
1: Paint Arrives
2: Paint A - 1FS - Joe Painter
3: Paint B - 1FS - Joe Painter
4: Paint C - 1FS - Joe Painter
and resource level to establish the sequencing. If there is a preferred
order to the walls, in contrast to a REQUIRED order, set task priorities
in
descending order on the tasks.
If the paint is to be delivered on a certain date, this is a case where a
Start No Earlier Than constraint is entirely appropriate. The earliest
date
the painting can start is the date the paint arrives but if the prep work
still isn't done, it's going to have to start later. So the actual
predecessor of the painting tasks would be Prep Work and the painting
tasks
themselves would each have a SNET of the date the vendor has promised to
deliver the paint. In that case the Paint Arrives milestone can be
dropped
altogether unless it's something important enough to monitor it in the
schedule, like you need to know the date it arrived because that triggers
the payment on the invoice or something like that.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://project.mvps.org/faqs.htm for the FAQs
This might be a silly Qs to ask but please help me out:-
There are three walls to be painted at different times, lets say one
after
the other.
e.g.
A -> B -> C
I need to plug a milestone (D) before these activities for arrival of
Paint
before stating of painting on the first wall.
Other points to be noted:-
1) The order priority of painting the walls may change in future, hence
I
need to connect "D" with all the walls A,B & C.
2) My programme is scheduled from the Start date.
I have tried my best but in vain.
HOW TO DO THIS?