Hi,
I am trying to adjust one of my resources actuals. When I have selected the
user I see there is already reported time (shown in black numbers in the
grid). If I modify this time to the right numbers I receive the message about
the update sent to the PM. After the PM accepts the update nothing happens,
the black hours are still there and the actual work is not being updated on
the resource task pane. Where did I went wrong?
Your help is much appreciated
Mauricio
I am trying to adjust one of my resources actuals. When I have selected the
user I see there is already reported time (shown in black numbers in the
grid). If I modify this time to the right numbers I receive the message about
the update sent to the PM. After the PM accepts the update nothing happens,
the black hours are still there and the actual work is not being updated on
the resource task pane. Where did I went wrong?
Your help is much appreciated
Mauricio