B
Braker
I'm having trouble updating a project's early start using sql in the
timephased table. The task will update but it will shift the entire task
including the finish date. When I update using the interface in Project
professional or web access it will split the task and my finish date isn't
affected. I think my problem has something to do with the TD_Field_ID in the
MSP_Timephased_data table. I use the value "2" to update assignment actual
work. Thanks in advance for your help.
timephased table. The task will update but it will shift the entire task
including the finish date. When I update using the interface in Project
professional or web access it will split the task and my finish date isn't
affected. I think my problem has something to do with the TD_Field_ID in the
MSP_Timephased_data table. I use the value "2" to update assignment actual
work. Thanks in advance for your help.