I'm trying to change the hours for a resource on the same task, because of
the way we allocate resources here. In other words, if I have a task that
will take a resource 20 hours and he's going to work on it over two weeks, I
can put that as fixed duration (10 days) and put the work for 20 hours, and
Project will make that be 10 hours each week. But if I want the resource to
do 15 hours the first week, and 5 hours the next.
Can I do this without entering in two different tasks?