D
david
I am trying to understand certain MSP behavior which I have seen with both
2000 and 2003.
The first thing I am trying to understand is why Project splits the end of
fixed duration tasks in strange ways. Here is what I have done:
Settings:
Work starts on: Sunday
Default start time: 12:00 AM
Default end time: 12:00 AM
Hours per day: 24.00
Hours per week: 168.00
Days per month: 30
24 hr project calendar
Resource #1
Standard calendar
No availability configured
Task #1
Start date: 5/16/07
Duration: 5 days
Work: 0
Constraint date: 5/16/07
Constraint type: Start no earlier than
Predecessor(s): none
Successor(s): none
Lag: none
Type: fixed duration, effort-driven
Task #2
Identical to task #1.
---
After setting this project up I assign resource #1 to both tasks. The work
field for both tasks is now 24 hrs. Task #1 starts on Wednesday and ends
on Monday. Task #2 starts on Monday and ends on Saturday. Resource #1 is
scheduled for only 1 hr of work on Monday (for task #2). Task #2 splits on
Thursday after 7 hours of work and continue to show split (periods instead
of a bar on the Gantt chart) until Saturday, at which point the task ends.
Why does task #2 split at the end?
Why doesn't task 2 start on Monday at 8AM?
I have found that changing the tasks' start date changes this behavior. If
I remove the resources and start both tasks on Monday 5/14/07 and assign
resource #1 to task #1 then 40 hrs of work are performed on it over 5 days.
If I then assign resource #1 to task #2, 40 hrs of work will be done on it
as well but task #2's duration changes to 7 days. The task starts at 4PM
on Monday and continues until the following Monday on which 7 hrs of work
are scheduled. The "end split" no longer shows up.
Why does the duration of task #2 (fixed duration) change to 7 days?
I entered this last project setup again to be sure I described it right. I
accidentally created the tasks as "Fixed Units" and after assigning
resource #1 to task #1 the task spreads out to over 2 weeks so that 120 hrs
of work are done.
Why doesn't the duration change here to show how many days have gone by
between the start and finish dates? I thought that a 24 hr project
calendar would make a 5d duration 5 whole days.
I've worked with elapsed time before but in this case if I use 5 edays
instead then the resource is scheduled to work 24 hrs a day instead of 8
hrs per day as its calendar is configured.
I feel many of my problems are the result of trying to use 24 hr calendars
along with standard calendars. I do not see a way around this as I am
trying to schedule a lab which contains equipment that does work 24/7 as
well as shifts of people.
Thanks for any help,
David
2000 and 2003.
The first thing I am trying to understand is why Project splits the end of
fixed duration tasks in strange ways. Here is what I have done:
Settings:
Work starts on: Sunday
Default start time: 12:00 AM
Default end time: 12:00 AM
Hours per day: 24.00
Hours per week: 168.00
Days per month: 30
24 hr project calendar
Resource #1
Standard calendar
No availability configured
Task #1
Start date: 5/16/07
Duration: 5 days
Work: 0
Constraint date: 5/16/07
Constraint type: Start no earlier than
Predecessor(s): none
Successor(s): none
Lag: none
Type: fixed duration, effort-driven
Task #2
Identical to task #1.
---
After setting this project up I assign resource #1 to both tasks. The work
field for both tasks is now 24 hrs. Task #1 starts on Wednesday and ends
on Monday. Task #2 starts on Monday and ends on Saturday. Resource #1 is
scheduled for only 1 hr of work on Monday (for task #2). Task #2 splits on
Thursday after 7 hours of work and continue to show split (periods instead
of a bar on the Gantt chart) until Saturday, at which point the task ends.
Why does task #2 split at the end?
Why doesn't task 2 start on Monday at 8AM?
I have found that changing the tasks' start date changes this behavior. If
I remove the resources and start both tasks on Monday 5/14/07 and assign
resource #1 to task #1 then 40 hrs of work are performed on it over 5 days.
If I then assign resource #1 to task #2, 40 hrs of work will be done on it
as well but task #2's duration changes to 7 days. The task starts at 4PM
on Monday and continues until the following Monday on which 7 hrs of work
are scheduled. The "end split" no longer shows up.
Why does the duration of task #2 (fixed duration) change to 7 days?
I entered this last project setup again to be sure I described it right. I
accidentally created the tasks as "Fixed Units" and after assigning
resource #1 to task #1 the task spreads out to over 2 weeks so that 120 hrs
of work are done.
Why doesn't the duration change here to show how many days have gone by
between the start and finish dates? I thought that a 24 hr project
calendar would make a 5d duration 5 whole days.
I've worked with elapsed time before but in this case if I use 5 edays
instead then the resource is scheduled to work 24 hrs a day instead of 8
hrs per day as its calendar is configured.
I feel many of my problems are the result of trying to use 24 hr calendars
along with standard calendars. I do not see a way around this as I am
trying to schedule a lab which contains equipment that does work 24/7 as
well as shifts of people.
Thanks for any help,
David