I have developed a series of projects in an project database file. One of
projects is a resource pool. I was able to link the other projects and they
can all access this resource pool. However, I don't understand why when
someone assigns a resource to a task from the resource pool, a new record is
created in the MSP_RESOURCE data with the project id and the resource
information. If the purpose of a resource pool is to manage resources
centrally, why should project create another record of this resource when it
is used? Do these multiple instances of the resource maintain a
relationship, so if I alter the calendar in the resource pool project, that
will be reflected in all the instances of this resource in the other projects?
projects is a resource pool. I was able to link the other projects and they
can all access this resource pool. However, I don't understand why when
someone assigns a resource to a task from the resource pool, a new record is
created in the MSP_RESOURCE data with the project id and the resource
information. If the purpose of a resource pool is to manage resources
centrally, why should project create another record of this resource when it
is used? Do these multiple instances of the resource maintain a
relationship, so if I alter the calendar in the resource pool project, that
will be reflected in all the instances of this resource in the other projects?