How exactly can I turn off protecting actuals. Regardless of whether or not
this is a good idea or why I might want to do this, how do I do it?

(We need to delete tasks that have actuals in them. They are not real tasks
in the project.)
 
D

Dale Howard [MVP]

Jerry --

By turning off Managed Time Periods. Log into PWA with administrator
permissions, then click Admin - Customize Project Web Access. In the Time
Period Settings section, select the Non Managed Periods option and then
click the Save Changes button. Hope this helps.
 