T
Tusa123
Hi everyone, I've done a quick search on the site and cant seem to fin
an answer so I figure I'd throw it out there for an answer. I a
creating a workback and trying to minimize clutter. That said- right no
I have a cell that calculates days out from today's date. Within tha
same cell I want to have days/weeks whereby that individual cel
calculates days out and the next formula uses that value and divides b
7 to calculate weeks out using that first formula, with the end valu
resulting something like: “28 / 4” (days out / weeks out). 28 is th
first calculation [=IF(F18>0,F18-TODAY(),"-")] and 4 representing th
the results of the first calculation divided by 7.
Any help would be huge!
Many thanks
an answer so I figure I'd throw it out there for an answer. I a
creating a workback and trying to minimize clutter. That said- right no
I have a cell that calculates days out from today's date. Within tha
same cell I want to have days/weeks whereby that individual cel
calculates days out and the next formula uses that value and divides b
7 to calculate weeks out using that first formula, with the end valu
resulting something like: “28 / 4” (days out / weeks out). 28 is th
first calculation [=IF(F18>0,F18-TODAY(),"-")] and 4 representing th
the results of the first calculation divided by 7.
Any help would be huge!
Many thanks