Two Week Look Ahead Filter

B

bsky201

I am wanting to create a tew week look ahead filter in MS Project 2003. My
first inclination is to modify the "Task Range" built in filter but am not
sure of the prameters to use. Can someone suggest the proper way to create
this filter?
 
V

vanita

Hi

Use the 'Date range' filter, starting from current date to two weeks ahead.

I hope it helps.
Vanita
 