W
WSH
Hi,
In Total Cost column in MS Project 2003, I type the cost of the project/task
manually. I then assign a resource to that task/project and the cost changes
to something higher or lower at times. I then have to retype the cost again.
Is there a way to stop it from changing? I just need to type in the cost of
the projects manually disregarding resource costs/fixed costs etc. Please let
me know how to do it if there is a way.
Thank you for all the help ppl.
In Total Cost column in MS Project 2003, I type the cost of the project/task
manually. I then assign a resource to that task/project and the cost changes
to something higher or lower at times. I then have to retype the cost again.
Is there a way to stop it from changing? I just need to type in the cost of
the projects manually disregarding resource costs/fixed costs etc. Please let
me know how to do it if there is a way.
Thank you for all the help ppl.