Unable to delete or move some sub-tasks in MS Project 2003

C

Chillie

Some of my sub tasks in my project I just can't delete, cut or move.
No error message, nothing, it just ignores the reqest.
This also happens when I create a brand new project
There are no dependencies between any tasks.

Any help gratefully received.
 
J

JulieS

Hi Chillie,
See http://support.microsoft.com/kb/834684

I am not sure if this is your specific problem, but the patch they refer to
in the KB article does describe difficulties with subtasks. If you have not
applied the patch (and SP1), I would try that first.
Hope this helps. Let us know how you get along.