Unable to display Work in days in Resource Usage View.

L

Ludo

Using Microsoft Project Server 2002 SP1 with Microsoft Project Profesionnal
2002 SP1

When i change the schedule options to display work in days, it works but on
the resource usage view, I still see the resource work in hours (the
assignments beneath are in days).
This behavior occurs only when connected to project server. If I work
Offline, the behaviour is correct (resource information is displayed in days
as well as resource assignemnts in resource usage view.

Is it a known issue?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top