S
Scott F
My work includes planning turnaround maintenance in a Chemical Manufacturing
plant. The operations people work 12 hour shifts (24/7/365). They have a 28
day cycle with 4 distinct shifts that cover a 28 day revolving cycle. I've
created separate calendars for each shift.
When we undergo maintenance turnarounds, many of the people work during
their non-working time, which is paid at an overtime rate (...along with
those working their regular working time).
When assigning resources to tasks, I was hoping that if a resource was
scheduled to work on an assigned task during the non-working period of their
resource calendar, that the overtime rate would be applied. Instead it moved
the task to their first working day. I then checked the "Ignore Resource
Calendar" Checkbox, which moved the task back to the scheduled time, but the
overtime rate wasn't applied.
Looking through the task usaage table, I added the Overtime work field and
updated the hours to show the work as overtime. This reduced the duration of
the task to a zero duration however. From a scheduling standpoint, this is
not what I want to see. Even though the task is OT, I need the duration to be
the same so the overall planned timeline is correct.
Ideally, it would be perfect if when assigning the resource, a checkbox
would beome enabled to allow the overtime rate be applied without reducing
task duration. I still want the task to be effort driven...it's just that
some resources will be paid overtime because they're working on their
scheduled day off.
Does anyone have experience in setting up Project to accomodate this kind of
scenario?
Thanks
Scott
plant. The operations people work 12 hour shifts (24/7/365). They have a 28
day cycle with 4 distinct shifts that cover a 28 day revolving cycle. I've
created separate calendars for each shift.
When we undergo maintenance turnarounds, many of the people work during
their non-working time, which is paid at an overtime rate (...along with
those working their regular working time).
When assigning resources to tasks, I was hoping that if a resource was
scheduled to work on an assigned task during the non-working period of their
resource calendar, that the overtime rate would be applied. Instead it moved
the task to their first working day. I then checked the "Ignore Resource
Calendar" Checkbox, which moved the task back to the scheduled time, but the
overtime rate wasn't applied.
Looking through the task usaage table, I added the Overtime work field and
updated the hours to show the work as overtime. This reduced the duration of
the task to a zero duration however. From a scheduling standpoint, this is
not what I want to see. Even though the task is OT, I need the duration to be
the same so the overall planned timeline is correct.
Ideally, it would be perfect if when assigning the resource, a checkbox
would beome enabled to allow the overtime rate be applied without reducing
task duration. I still want the task to be effort driven...it's just that
some resources will be paid overtime because they're working on their
scheduled day off.
Does anyone have experience in setting up Project to accomodate this kind of
scenario?
Thanks
Scott