Unable to publish a task in a plan

E

ein

Hi,
I'm using project server 2003. I opened a task and assigned a local
resource. I replaced that resource with an enterprise resource. When I tried
to publish the task, I got the following message: "an update has not been
sent yet to resources who have been removed from task assigment.an update
will be sent now". the task is not being published and also other tasks are
dissabled for publishing.

What should I do?

Ein
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top