Unable to Publish Assignments

M

Minhchau

We're using Project 2003. I assigned hours to an external "work" resource in
Project Pro, and Publish All Information. When I tried to put in hours for
that external resource using "Adjust Actual" option, there's no open window
to enter the hours for the assigned task in that screen.
Please show me how to show the open window in PWA under "Adjust Actual"
screen for the assigned task.

Thanks,
 
M

Marc Soester

Hi Minhchau,

When you refer to the "external" resource, do you refer to a "generic"
resource?. If this is the case, then you will not be able to use "adjust
actuals" in PWA. A generic resource is seen as a "non" real resource who can
not enter time, therefore you will not be able to enter time for a generic
resource.

Should you want to enter time for this external resource, you will need to
make sure that this resource is a non generic resource, you then should have
the ability to enter the time
I hope this helps
 