S
SteveP
We are using MS Project Server Professional 2007 (and PWA) SP1
We have been using a project for some time with no issues, however,
recently when a task has two users assigned, these users are unable to
see the task in the My Tasks list in PWA(although it shows correctly
in Professional). It seems that this is happening when a second user
is assigned to an already existing task. We have not yet narrowed
this down to just being one project, but other projects on the server
do not seem to experience this problem.
We have not made any permission changes or any other setting changes.
Any thoughts on why this may be happening?
Thanks
Steve
We have been using a project for some time with no issues, however,
recently when a task has two users assigned, these users are unable to
see the task in the My Tasks list in PWA(although it shows correctly
in Professional). It seems that this is happening when a second user
is assigned to an already existing task. We have not yet narrowed
this down to just being one project, but other projects on the server
do not seem to experience this problem.
We have not made any permission changes or any other setting changes.
Any thoughts on why this may be happening?
Thanks
Steve