J
Jesse
% work complete is 100% but % complete is less than 100%....so the indicator
field does not show the completed check.
- shouldn't % complete go to 100% if % work complete is 100%?
- I can edit the task and make % complete 100%. publish all...and the task
is 100% complete and 100% work complete. great
- if I edit a different task in such a way that I get the "out of sync"
message...and the task and field I updated reverts to the value of the
protected actual.....the task that I changed earlier to 100% complete reverts
back to less than 100% complete. Why??
- how can I make a task 100% complete when the % work complete is 100%?
MS Project Server 2003
- the Tracking Settings is "hours of work done per day or week"
- the Lock Down Defaults is "force project managers to..."
- managed periods is enabled
MS Project 2003
- task type is fixed duration
field does not show the completed check.
- shouldn't % complete go to 100% if % work complete is 100%?
- I can edit the task and make % complete 100%. publish all...and the task
is 100% complete and 100% work complete. great
- if I edit a different task in such a way that I get the "out of sync"
message...and the task and field I updated reverts to the value of the
protected actual.....the task that I changed earlier to 100% complete reverts
back to less than 100% complete. Why??
- how can I make a task 100% complete when the % work complete is 100%?
MS Project Server 2003
- the Tracking Settings is "hours of work done per day or week"
- the Lock Down Defaults is "force project managers to..."
- managed periods is enabled
MS Project 2003
- task type is fixed duration