We have a Project Server 2007 installation. We have timesheets turned off,
and are using the PWA My Tasks view to enter actual hours. We have the
Tracking Method set to 'Actual work done and work remaining', and the 'Force
project managers to use the progress reporting method specified above for all
projects' and 'Resources should report their hours worked every day' boxes
checked.
For most of our projects, when they are published, the My Tasks view shows
'0h of 8h (0 %)' in the Progress column - and when we click on the cell, it
pops up a window with each day of the week for data entry. On some projects,
though, we just see '0h' in the Progress column and cannot enter time by day.
Does anyone know what is causing this, or have any hints? We recently
installed SP1 on the desktops but not the servers (got delayed - don't ask
:=) and I'm wondering if this is the cause. It seems to be for
recently-pubslihed projects.
Has anyone else seen this?
and are using the PWA My Tasks view to enter actual hours. We have the
Tracking Method set to 'Actual work done and work remaining', and the 'Force
project managers to use the progress reporting method specified above for all
projects' and 'Resources should report their hours worked every day' boxes
checked.
For most of our projects, when they are published, the My Tasks view shows
'0h of 8h (0 %)' in the Progress column - and when we click on the cell, it
pops up a window with each day of the week for data entry. On some projects,
though, we just see '0h' in the Progress column and cannot enter time by day.
Does anyone know what is causing this, or have any hints? We recently
installed SP1 on the desktops but not the servers (got delayed - don't ask
:=) and I'm wondering if this is the cause. It seems to be for
recently-pubslihed projects.
Has anyone else seen this?