Minhchau
We've been using Project 2003 since March 2003. We're using SQL server with
timesheet system (managed period every two weeks). Recently, we temporarily
switched the managed period to unmanaged period for a day so that our staff
can manually input hours for external resources. We then switched back to
the managed period. When we updated project progress, some of the timesheet
resources who had actual hours in the projects didn't show up for us to
approved. In other words, the timesheets seemed to be unlinked to the
project. When I looked at the Web Access screen, under Resources/Adjust
Actual, the hours that these timesheet resources charged to the project were
there (in blue).
Please show me how to make this work again.
Thanks,
timesheet system (managed period every two weeks). Recently, we temporarily
switched the managed period to unmanaged period for a day so that our staff
can manually input hours for external resources. We then switched back to
the managed period. When we updated project progress, some of the timesheet
resources who had actual hours in the projects didn't show up for us to
approved. In other words, the timesheets seemed to be unlinked to the
project. When I looked at the Web Access screen, under Resources/Adjust
Actual, the hours that these timesheet resources charged to the project were
there (in blue).
Please show me how to make this work again.
Thanks,