Tammy
Hi,
We use the resource pool to create a customized view which is a report by
project. For some reason, this report has been showing unassigned tasks with
"work" hours that are not assigned in each individual project plan. When the
master is run and left open when running our view out of the resource pool,
these unassigned hours go away. The hours go away also when an individual
project plan is opened.
My questions...
Where is it getting the hours?
Why is it showing hours that are not in the plan until we open either the
individual plan or the master?
Why does it show hours that are not in the MSP?
Help!
Tammy
We use the resource pool to create a customized view which is a report by
project. For some reason, this report has been showing unassigned tasks with
"work" hours that are not assigned in each individual project plan. When the
master is run and left open when running our view out of the resource pool,
these unassigned hours go away. The hours go away also when an individual
project plan is opened.
My questions...
Where is it getting the hours?
Why is it showing hours that are not in the plan until we open either the
individual plan or the master?
Why does it show hours that are not in the MSP?
Help!
Tammy