G
Gilgamesh
Hello,
I'm using Project Pro 2003 and I have some VBA macros that extract time
scaled work data for each resource in the project.
However when I look at the Resource Usage View there is the Unassigned row
for tasks that do not have a resource assigned.
Is there any way of getting the time scaled data extracted using VBA for
these unassigned tasks (other than looping through all tasks and checking
them).
Thanks
I'm using Project Pro 2003 and I have some VBA macros that extract time
scaled work data for each resource in the project.
However when I look at the Resource Usage View there is the Unassigned row
for tasks that do not have a resource assigned.
Is there any way of getting the time scaled data extracted using VBA for
these unassigned tasks (other than looping through all tasks and checking
them).
Thanks