B
Brad Ems
The company I work for is considering moving from a custom MS Excel
spreadsheet for project estimation to MS Project. I've been tasked with
evaluating this potential move. I can see great utility in providing the
time dimension to project managers of successful jobs, but I am also
encountering what seems to me a bewildering limitation in Project.
Specifically, there seems to be no inherent way to calculate price aside
from creating a copy of the "cost" version of the project file and
re-entering the pricing rates into the resource table. Alternately, one can
enter the unburdened, burdened and pricing information into each resource's
cost table, but this also limits the usefulness of the application as one A -
cannot see side-by-side comparisons of costs versus price (and the resultant
profit margin) B - must go into the Task Usage view and change all resource
rates depending on which estimate is desired at any moment.
Custom fields seem to be local-only...pulling rate data from the Resource
Table isn't possible within the context of the Task Table, where the task
durations reside. What I am wanting to do is to include another column in my
Gantt/Task Usage views that will do exactly what the current "Cost" column
does, but will pull work and rate data from different fields.
Is there some way to do this within Project's existing structure? Thanks to
any and all that can assist.
BWE
spreadsheet for project estimation to MS Project. I've been tasked with
evaluating this potential move. I can see great utility in providing the
time dimension to project managers of successful jobs, but I am also
encountering what seems to me a bewildering limitation in Project.
Specifically, there seems to be no inherent way to calculate price aside
from creating a copy of the "cost" version of the project file and
re-entering the pricing rates into the resource table. Alternately, one can
enter the unburdened, burdened and pricing information into each resource's
cost table, but this also limits the usefulness of the application as one A -
cannot see side-by-side comparisons of costs versus price (and the resultant
profit margin) B - must go into the Task Usage view and change all resource
rates depending on which estimate is desired at any moment.
Custom fields seem to be local-only...pulling rate data from the Resource
Table isn't possible within the context of the Task Table, where the task
durations reside. What I am wanting to do is to include another column in my
Gantt/Task Usage views that will do exactly what the current "Cost" column
does, but will pull work and rate data from different fields.
Is there some way to do this within Project's existing structure? Thanks to
any and all that can assist.
BWE