Unconscious Acceptance of task assignments

R

RLP

Tasks are accepted simply by displaying the task list. The resource may not even see task assignment, especially if the task list is longer than the screen

The problem is task acceptance is a quality tracking and resource performance auditing record

If the resource does not consciously take action to accept the assignment he/she can simply say that they did not see the new assignment. Receiving the notification e-mail does not solve the problem

Am I missing a setting in Project Server
What is the solution

Thank

Lester Powel
Chief Project Manage
SPIK SZM

www.szma.co
(e-mail address removed)
 
G

Gary L. Chefetz [MVP]

Lester:

Please don't cross post.




RLP said:
Tasks are accepted simply by displaying the task list. The resource may
not even see task assignment, especially if the task list is longer than the
screen.
The problem is task acceptance is a quality tracking and resource performance auditing record.

If the resource does not consciously take action to accept the assignment
he/she can simply say that they did not see the new assignment. Receiving
the notification e-mail does not solve the problem.
 