M
miao jie
I have a comfusion about resource view, After I deal with the overallocated resource ( each of resource under 8 hour per day), the resource name still keep the red color.
then I check the resource graph view, found the peak unit is over 100% in some days( display with red color) , for other format( work, overallocation....) are displayed with blue color. I'm also check the each of resource's max unit is 100%
what's the Peak unit means? why it showed with red color ??
then I check the resource graph view, found the peak unit is over 100% in some days( display with red color) , for other format( work, overallocation....) are displayed with blue color. I'm also check the each of resource's max unit is 100%
what's the Peak unit means? why it showed with red color ??