D
David Rio
Hello
Probably I do not use MS Project as I should because I so often have the same problem :
I have a project with several tasks (fix work).
I define a custom calendar for each resource in order to take into account vacations.
But when MS Projects splits the work among the resources, it does not take the best of them and I have under allocated resources whereas this resource could continue to work on this task and make it finish earlier.
What am I doing wrong ?
Probably I do not use MS Project as I should because I so often have the same problem :
I have a project with several tasks (fix work).
I define a custom calendar for each resource in order to take into account vacations.
But when MS Projects splits the work among the resources, it does not take the best of them and I have under allocated resources whereas this resource could continue to work on this task and make it finish earlier.
What am I doing wrong ?