K
Kathy S
I have a plan where the duration alternates between days and months
due to federal regulations. This question will focus on the months
duration.
All tasks use the calendar "Weekend Only" which includes weekends,
there are no holidays, the time is 8am-12pm; 1pm-5pm.
Under Tools > Options > Calendar, the days per month is 20.
Both tasks are Fixed Duration and NOT Effort Driven.
Constraint type for both tasks are asap.
There are no resources.
Tasks 1 & 2 both have months duration.
Task 2 has a Task 1FS predecessor.
Task 2 start date is 10/26/08 with 3 mos. duration for a finish date
of 12/24/08.
It is obvious that 3 mos from 10/26/08 is not 12/24/08. The correct
finish date should be 1/26/09.
If I change Under Tools > Options > Calendar, the days per month from
20 to 31, the duration is automatically decreased to 2.9 mos. I then
increase the duration from 2.9 mos to 3 mos and the finish date is
1/26/09. The problem with this change is that all months do not have
just 31 days so other tasks will be off.
Is there a way to dictate specific months have 31 days? What is the
best way to ensure that the finish dates correctly reflect the
duration from the start date? Does anyone have a good explanation as
to how MSP calculates.
Thanks,
Kathy
due to federal regulations. This question will focus on the months
duration.
All tasks use the calendar "Weekend Only" which includes weekends,
there are no holidays, the time is 8am-12pm; 1pm-5pm.
Under Tools > Options > Calendar, the days per month is 20.
Both tasks are Fixed Duration and NOT Effort Driven.
Constraint type for both tasks are asap.
There are no resources.
Tasks 1 & 2 both have months duration.
Task 2 has a Task 1FS predecessor.
Task 2 start date is 10/26/08 with 3 mos. duration for a finish date
of 12/24/08.
It is obvious that 3 mos from 10/26/08 is not 12/24/08. The correct
finish date should be 1/26/09.
If I change Under Tools > Options > Calendar, the days per month from
20 to 31, the duration is automatically decreased to 2.9 mos. I then
increase the duration from 2.9 mos to 3 mos and the finish date is
1/26/09. The problem with this change is that all months do not have
just 31 days so other tasks will be off.
Is there a way to dictate specific months have 31 days? What is the
best way to ensure that the finish dates correctly reflect the
duration from the start date? Does anyone have a good explanation as
to how MSP calculates.
Thanks,
Kathy