J
John
I am setting up a project which has 3 outline levels. The detail tasks represent stages of development of chapters of a book, so they roll up to a summary task which represents the progress of the chapter as a whole. There are a number of chapters which each roll up to the top level summary of the book as a whole.
At the detail task level, time is a good measure of progress for the way we operate, so when our second level task is 50% complete that is reflected sufficiently by progressing the tasks accordingly. However as each chapter is significantly different in size and complexity to develop, the second level tasks are not represented well by time invested.
We wish to be able to weight the second level tasks according to a criteria independent of effort. i.e. a particular chapter may be 15% of the entire book which is our ultimate measure of progress.
Can anyone help me understand if there is any way to do this in Project?
Thanks
At the detail task level, time is a good measure of progress for the way we operate, so when our second level task is 50% complete that is reflected sufficiently by progressing the tasks accordingly. However as each chapter is significantly different in size and complexity to develop, the second level tasks are not represented well by time invested.
We wish to be able to weight the second level tasks according to a criteria independent of effort. i.e. a particular chapter may be 15% of the entire book which is our ultimate measure of progress.
Can anyone help me understand if there is any way to do this in Project?
Thanks