'Undue' Updates.

V

vandermt

Hi,
Project Server 2007, SP1
We are in the process of putting together a best practice for accepting
updates for our project managers.
We read the posts on accepting updates using project Professional and we
plan to use them.
Our question is this, After we accept and view an update using project
professional, if the project manager sees something he does not like in the
draft is there a way to revert back to what is in the published database?
Thanks
 
M

Marc Soester [MVP]

Hi vandermt,
the purpose of checking the update before accepting the project is to ensure
that the PM is happy with the update. There is no functionality the describes
a "rollback" once the project changes have been accepted.

Having said this, there is a workaround ( not to nice). If you use the
backup/restore functionality of Project Server, the PM could revert back the
the previous backuped Schedule. He would then need to communicate to the team
members to re-submit the change and then can accept it agian ( I know,
combersome).

I hope this is what you are after
 
V

vandermt

thanks for your response

sometimes we are seeing actuals in the future and cannot figure out where
they are comming from
 
V

vandermt

G

Gary L. Chefetz

The most current update available is the February CU. This just came out and
I haven't tested it yet. You should at least get the December Cumulative
Update installed. Make sure you do your research in the Knowledgebase to
make sure your system is updated correctly.

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com
 
V

vandermt

Gary,
I am not familiar with CUs. Can you give me a 'best practice'?
Does the December CU contain everything we need?
Why do you need to test the February CU?
 
G

Gary L. Chefetz

CU = Cumulative Update. Between each service pack release, Microsoft
releases what they call "hot fixes" for bugs reported by customers. These
are generally released as they become available. Every two months, Microsoft
now bundles (This is a new go-forward strategy for the Office Suite) all of
the updates into a Cumulative Update and each CU contains everything that
was previously released. Eventually, these bundles become a Service Pack.
Understand that hot-fixes and CUs are not fully regression tested as Service
Packs are supposed to be. I say this because Service Packs can have
regression errors but they have gone through more rigorous testing than hot
fixes and CUs.

Some IT shops refuse to install anything but Service Packs. IMO, this is too
limiting with Project Server 2007 as the fixes that Microsoft has been
releasing have been too important to shelve because of arbitrary rules. You
need to decide what your best-practice is going to be and so much depends on
what constraints your organization imposes on you and how the system is
functioning. If you aren't encountering problems, then you can ignore an
update. If you have a problem that is fixed by an update, wouldn't you want
to install it?

When I say that I haven't tested it, I'm referring to our company's policy
not to recommend updates to our clients without first installing the updates
in our lab and running our own set of tests. Sometimes we discover issues
that Microsoft missed, sometimes we don't. One thing is certain, once the
update is released and people encounter problems with it, you are very
likely to hear about it first in this community, or through one of the
bloggers who participate here!

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com
 
V

vandermt

Gary,
Thanks for the explaination.
I take it you are recommending the December Cululative update?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top