I'm the project scheduler on a very large project which has a project
schedule w/nearly 2000 lines. We've experienced several instances where
baseline dates have changed but we have not re-baselined the schedule or
those particular tasks.
We have set baselines on newly added tasks (using the Tools -> Tracking ->
Save Baseline -> Selected Tasks. Initially we put checks in the boxes for
"To All Summary Tasks" and "From Subtsks into Selected Summary Task(s)",
however, we have since unchecked those two boxes and now only baseline
specific tasks and no summary tasks.
Since my colleague and I are the only two people with write access to the
..mpp file and we know we didn't touch the affected tasks, it seems that these
dates are changing on their own.
Does anyone have any insight into what might be causing the changes in the
baseline dates of tasks we have not selected for re-baselining.
Thanks in advance!
schedule w/nearly 2000 lines. We've experienced several instances where
baseline dates have changed but we have not re-baselined the schedule or
those particular tasks.
We have set baselines on newly added tasks (using the Tools -> Tracking ->
Save Baseline -> Selected Tasks. Initially we put checks in the boxes for
"To All Summary Tasks" and "From Subtsks into Selected Summary Task(s)",
however, we have since unchecked those two boxes and now only baseline
specific tasks and no summary tasks.
Since my colleague and I are the only two people with write access to the
..mpp file and we know we didn't touch the affected tasks, it seems that these
dates are changing on their own.
Does anyone have any insight into what might be causing the changes in the
baseline dates of tasks we have not selected for re-baselining.
Thanks in advance!