M
Mike
Hello,
I have a resource that shows an overallocation, i.e. the resource's name
appears in red in the Resource Sheet, but upon examining the resource's time,
I can't find where the overlap exists.
None of the Work hours in Resource Usage appears in red even when changing
the timescale to view time by the hour. I even tried looking at the
resource's time by the minute, but couldn't find a way to change the scale of
Work hours into minutes (for each minute division of the scale, the resource
was shown to have worked "0.02h" rather than "1m" -- Project must round the
number since .02 hours equals 1.2 minutes; the same value is listed for
resources who are NOT overallocated).
Also:
- There are no warning messages after levelling that indicate a problem,
- The Resource Graph shows no red overages anywhere,
- Setting the resource's Max Units to 101% clears the overallocation.
Any suggestions would be appreciated...thank you.
I have a resource that shows an overallocation, i.e. the resource's name
appears in red in the Resource Sheet, but upon examining the resource's time,
I can't find where the overlap exists.
None of the Work hours in Resource Usage appears in red even when changing
the timescale to view time by the hour. I even tried looking at the
resource's time by the minute, but couldn't find a way to change the scale of
Work hours into minutes (for each minute division of the scale, the resource
was shown to have worked "0.02h" rather than "1m" -- Project must round the
number since .02 hours equals 1.2 minutes; the same value is listed for
resources who are NOT overallocated).
Also:
- There are no warning messages after levelling that indicate a problem,
- The Resource Graph shows no red overages anywhere,
- Setting the resource's Max Units to 101% clears the overallocation.
Any suggestions would be appreciated...thank you.