E
ecipm
Instead of using partial percentages for a resource, I am assigning a
resource to an overhead task the first two weeks of each month. I am
expecting Project to fill the gaps with the main project tasks. For some
reason, Project is not filling the "free" 2 weeks each month. Instead, the
project tasks do not start until after the last overhead task is complete. I
have the verified with the resource view that this time is indeed empty (not
assigned anything else that I may have forgotten about). I can't see why
these gaps would not be filled. Can anyone see what I am doing wrong or
suggest a different approach.
resource to an overhead task the first two weeks of each month. I am
expecting Project to fill the gaps with the main project tasks. For some
reason, Project is not filling the "free" 2 weeks each month. Instead, the
project tasks do not start until after the last overhead task is complete. I
have the verified with the resource view that this time is indeed empty (not
assigned anything else that I may have forgotten about). I can't see why
these gaps would not be filled. Can anyone see what I am doing wrong or
suggest a different approach.