Looking for some help with identifying projects once I have saved them to
Excel, using ‘save as’ and the export wizard
The basic problem I have is that I can identify a single project by the
project name (as completed in the properties box) and all is well for a
single project.
However when I group a set of project together and have a summary project
i.e. I have inserted sub projects into a master plan. I want to be able to
identify all of the sub projects as part of the summary project. For example :
Summary Project called “Summary1â€
Sub Projects, A, B, C & D
The projects names that get exported by MSP into Excel are A, B, C & D yet
from a reporting point of view I want to know that they are actually Summary1
But I cant find a field that represents the summary project all I get is A,
B, C or D as the project name.
I thought about adding a unique text filed to the project, but I am
conscious of having to update this column every time a new task was entered
into the project.
Any idea how I can uniquely identify a summary project on a sub project ?
Thanks
Looking for some help with identifying projects once I have saved them to
Excel, using ‘save as’ and the export wizard
The basic problem I have is that I can identify a single project by the
project name (as completed in the properties box) and all is well for a
single project.
However when I group a set of project together and have a summary project
i.e. I have inserted sub projects into a master plan. I want to be able to
identify all of the sub projects as part of the summary project. For example :
Summary Project called “Summary1â€
Sub Projects, A, B, C & D
The projects names that get exported by MSP into Excel are A, B, C & D yet
from a reporting point of view I want to know that they are actually Summary1
But I cant find a field that represents the summary project all I get is A,
B, C or D as the project name.
I thought about adding a unique text filed to the project, but I am
conscious of having to update this column every time a new task was entered
into the project.
Any idea how I can uniquely identify a summary project on a sub project ?
Thanks