I am trying to build a project schedule and everytime I allocate one or more
resources to a task the units changes to 33% or 50% randomly. I want all the
resources to work on tasks a full 100%. How do I acheive that?
Thanks
 
M

Mike Glen

Hi projuser ,

Welcome to this Microsoft Project newsgroup :)

That's how Project works when you assign more than one resource to a task.
I've explained this fully in my series on Microsoft Project in the TechTrax
ezine, particularly # 10 – Multiple Resource Assignments, at this site:
http://tinyurl.com/2xbhc (Perhaps you'd care to rate it before leaving the
site, :) Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP

wrote:
 
S

Steve House [MVP]

Can you be more specific? Project doesn't just arbitrarily change
assignments. What are you doing or editing when you see the change? What
are the task types you have set and what fields have you manually input for
them before assigning resources? How are you going about making the
assignments?
 