Unit (%) does not show up in task usage view below gantt chart vie

M

Michael Vestel

In the view below the Gantt chart main view, you can choose various other
things to display. i would like to display certain info about a task i
choose.

Close to what i want is the Task Usage view. it shows work for each resource
for that task. great. But i'd like to show Cost, Work and most importanlty in
this view, is Units (percent). but do not see a way to add that column. any
thoughts?
 
D

Darrell

Michael,

I think what you want is in the Form View, which I think is the default when
you split the screen. If not you can make the lower section the active view
and select the Task Form from View>More Views. Now right click in the gray
area on the right side of the Task Form and select the information you are
interested in.

Darrell
 
M

Michael Vestel

Yes, very helpful. Thanks.

But i can not modfiy the columns or find a view to show all three:
cost
work
Units

any suggestions?
 
M

Mike Glen

Hi Michael,

You can't modify these forms. I would just insert the Cost column in the
table to the left of the Gantt Chart.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top