A
Anthony Moore
Could some one please clarify units. If you are writing a scope or
doing work and have allocated 1 full day then do you allocate the
assigned resource as 100%.
And if you have two people working on the task does mean you allocate
50% each resource for that one full day.
And finally if you are to work on a task but only spend 2 hours out of
the full day allocated how do you put that down in units.
Regards
Anthony Moore
doing work and have allocated 1 full day then do you allocate the
assigned resource as 100%.
And if you have two people working on the task does mean you allocate
50% each resource for that one full day.
And finally if you are to work on a task but only spend 2 hours out of
the full day allocated how do you put that down in units.
Regards
Anthony Moore