I am seeing the following scenario in MSPS 2003:
I have a Fixed Units, Effort driven task.
I set the duration.
I now need to extend the duration, so I manually adjust Duration.
My Units jumps up to some rediculous amount but my work doesn't change.
End result is that I am seeing things like 219 day duration (which is
actually correct for this purpose), 153.85 Work, and 92% Units.
This math doesn't add up. What could be causing this??