Units are wrong

J

JenGoSto

I am seeing the following scenario in MSPS 2003:

I have a Fixed Units, Effort driven task.
I set the duration.
I now need to extend the duration, so I manually adjust Duration.
My Units jumps up to some rediculous amount but my work doesn't change.

End result is that I am seeing things like 219 day duration (which is
actually correct for this purpose), 153.85 Work, and 92% Units.

This math doesn't add up. What could be causing this??
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top