MikeRMT
Project Server 2007: I want to be able to assign individual Resources for
some Project Tasks at a different Units% to the value associated with the
resource in the Enterprise Resource Pool. Changing the Units% and assigning
multiple resources allows tasks to start in parallel in the plan.
Unfortunately I have found that when I do this the Task assignments do not
show up in the My Tasks Views for the resources/users. However they do show
up correctly in the Project Centre view of the plan and in the Resource
Availability view for the Resource.
What do I need to do?
some Project Tasks at a different Units% to the value associated with the
resource in the Enterprise Resource Pool. Changing the Units% and assigning
multiple resources allows tasks to start in parallel in the plan.
Unfortunately I have found that when I do this the Task assignments do not
show up in the My Tasks Views for the resources/users. However they do show
up correctly in the Project Centre view of the plan and in the Resource
Availability view for the Resource.
What do I need to do?