D
Danielle Jacobs
Hello,
I'm creating a schedule for our division in MS Project.
I encountered the following problem: When I assign someone for e.g. (units)
20% in the resource sheet (he is available for 1 day a week; for 8 hours, no
fixed day of the week), MS Project schedules him for 5 days a week for 20% a
day maximum. However, I would like him to work with a flexible 20% a week.
For example, if the work is for 8 hours, the resource can work 8 hours on
one day. If he goes over his limit of 8 hours a week, only than I would like
MS Project to overallocate the resource, and not if he goes over the 20% on
one day.
Can anyone please help me fix this problem?
I'm creating a schedule for our division in MS Project.
I encountered the following problem: When I assign someone for e.g. (units)
20% in the resource sheet (he is available for 1 day a week; for 8 hours, no
fixed day of the week), MS Project schedules him for 5 days a week for 20% a
day maximum. However, I would like him to work with a flexible 20% a week.
For example, if the work is for 8 hours, the resource can work 8 hours on
one day. If he goes over his limit of 8 hours a week, only than I would like
MS Project to overallocate the resource, and not if he goes over the 20% on
one day.
Can anyone please help me fix this problem?