JodyJ
I have a fixed work task (i.e. the resource has indicated it will take them
20 hrs to complete the task). I assign them to the task and make the units
50% as they are only going to be able to work on this 'part time'. Overall
resource utilization looks good. When I close the plan and reopen it,
"units" have now changed to 88%.
I have many, many other tasks where this is occuring.
Any insight as to why?
20 hrs to complete the task). I assign them to the task and make the units
50% as they are only going to be able to work on this 'part time'. Overall
resource utilization looks good. When I close the plan and reopen it,
"units" have now changed to 88%.
I have many, many other tasks where this is occuring.
Any insight as to why?