This is a basic, but here goes...
When defining a resources availability in terms of units (100%, 50%,
25%), I assume that when you are providing this information at the
resource level (Resource Sheet), you are saying that this resource is
only available for project work, say 50% of the time regardless of the
project in question.
I also assume that when you are specifying Units when building the
team from the enterprise, you are indicating that this resource is
available 50% of the time for all tasks on this particular project.
I also assume that when you are specifiying Units at the Task/
Assignment Level, you are indicating that this resource is available
50% of the time for this task only.
Is this all correct? If not, please comment.
Thanks,
Andy Novak
UNT
When defining a resources availability in terms of units (100%, 50%,
25%), I assume that when you are providing this information at the
resource level (Resource Sheet), you are saying that this resource is
only available for project work, say 50% of the time regardless of the
project in question.
I also assume that when you are specifying Units when building the
team from the enterprise, you are indicating that this resource is
available 50% of the time for all tasks on this particular project.
I also assume that when you are specifiying Units at the Task/
Assignment Level, you are indicating that this resource is available
50% of the time for this task only.
Is this all correct? If not, please comment.
Thanks,
Andy Novak
UNT