R
rt
Good evening all,
I've read some threads on high units after accepting actuals into a
schedule with fixed duration, non-effort driven tasks. I couldn't find
anything about the latest fad in such schedules at our company though.
Instead of spreading remaining work over the remaining duration,
Project schedules all remaining work in the next week, thus causing
the units to skyrocket and the remaining duration to be shortened
significantly.
I've found it relatively simple to correct but it has to be done
manually after each update. After updating, I go to the resource usage
view, select the affected assignments (typically tasks with > 1
resource), set the contour to flat again and adjust the end date of
the assignment to align with the schedule and the other assignments.
Then I adjust work and I'm back in business.
I feel that such manual interventions are usually a sign that I'm
doing something wrong. Can anybody tell me what it is?
We're using Project Server 2003 SP2 with daily/weekly time reporting
of actual hours in managed periods.
I've read some threads on high units after accepting actuals into a
schedule with fixed duration, non-effort driven tasks. I couldn't find
anything about the latest fad in such schedules at our company though.
Instead of spreading remaining work over the remaining duration,
Project schedules all remaining work in the next week, thus causing
the units to skyrocket and the remaining duration to be shortened
significantly.
I've found it relatively simple to correct but it has to be done
manually after each update. After updating, I go to the resource usage
view, select the affected assignments (typically tasks with > 1
resource), set the contour to flat again and adjust the end date of
the assignment to align with the schedule and the other assignments.
Then I adjust work and I'm back in business.
I feel that such manual interventions are usually a sign that I'm
doing something wrong. Can anybody tell me what it is?
We're using Project Server 2003 SP2 with daily/weekly time reporting
of actual hours in managed periods.