Units to 0% Changes Duration to 0

M

Monika

I thought that fixed duration meant that duration will not change if units or
work numbers are changed.

I have tasks that are fixed duration, not effort-driven. I have already
assigned labor resources and their units (% available to work on this task).
If I take an assigned resource's units to 0%, the duration for some of the
tasks changes to 0.

Any ideas? Thanks!

Monika
 
D

Dale Howard [MVP]

Monika --

If you are using Project Server 2007, then this is the new default behavior
of the software. Sorry.
 
M

Monika

No, sorry I forgot to mention, we are using Project Server 2003.

The user thinks the duration is changing between the time he closes the file
and reopens it... I think it is the units but it doesn't happen on every task
and I can't see the difference.
 