Monika
I thought that fixed duration meant that duration will not change if units or
work numbers are changed.
I have tasks that are fixed duration, not effort-driven. I have already
assigned labor resources and their units (% available to work on this task).
If I take an assigned resource's units to 0%, the duration for some of the
tasks changes to 0.
Any ideas? Thanks!
Monika