unsubmitted timesheet never submitted

D

Daryl

HI all

I can't seem to get an of our staff's timesheet reminders to go away! Here is what is happening
- staff see reminder to submit timeshhet for a perio
- they enter time for the days they worked on for each day for the wee
- hit updat
- resource manger approved i
- PM approved i
- the unsubmitted timesheet reminder still shows up!!

In the timesheet summary view - I see that the status is (mixed). It seems like it is mixed because there are items in the summary that were not charged to (they have 0 hours) - some are actual project tasks, some are admin tasks - all with zero hours. There is no update available for the managers of these 0 hour tasks so they can never be approved as 0 hours (which I hope they would not have to do anway)

Is there any way to force the timesheet to be "Submitted"? Is there some setting that I have to change? We want to manage the time periods but we can't keep going like this, obviously

Everyone is still getting a reminder for every week that we had server up!!!! Please help

Dary
 
D

Dale Howard [MVP]

Daryl --

You need to open an incident with Microsoft support, and then will be able
to download the patch to fix this problem. Hope this helps.




Daryl said:
HI all,

I can't seem to get an of our staff's timesheet reminders to go away! Here is what is happening
- staff see reminder to submit timeshhet for a period
- they enter time for the days they worked on for each day for the week
- hit update
- resource manger approved it
- PM approved it
- the unsubmitted timesheet reminder still shows up!!!

In the timesheet summary view - I see that the status is (mixed). It
seems like it is mixed because there are items in the summary that were not
charged to (they have 0 hours) - some are actual project tasks, some are
admin tasks - all with zero hours. There is no update available for the
managers of these 0 hour tasks so they can never be approved as 0 hours
(which I hope they would not have to do anway).
Is there any way to force the timesheet to be "Submitted"? Is there some
setting that I have to change? We want to manage the time periods but we
can't keep going like this, obviously.
 
D

Daryl

Thanks Dale

This issue is noted in KB830820 - I called Microsoft and they sent me a Hotfix - I have not installed it yet, hopefully it works

Appreciate the heads up

Regards
Daryl
 
A

Arun

Daryl

Is ur issue solved by the hotfix. I am also having the same problem. Can you please advise me how to get rid of these error messaged

Thank
Arunes
(arunesh.u(removethis)@arig.com.b
 
L

Larry

Dale
In other postings I have read regarding this issue, Microsoft's hotfix 830820 has been referenced. Most of these other posts indicated results that were less than their expectations. Is this a viable fix for this bug? On Microsofts support page at http://support.microsoft.com/default.aspx?scid=kb;en-us;830820 they indicate that this fix will be incorporated into the next service pack but I have not found any indication of when that will be released. Does anyone have any ideas? Thanks!

- Larry
 
G

Gary L. Chefetz \(MVP\)

Larry:

It fixes the problem. What expectations were you referring to?

--

Gary L. Chefetz, MVP
"We wrote the book on Project Server
http://www.msprojectexperts

-
Larry said:
Dale -
In other postings I have read regarding this issue, Microsoft's hotfix
830820 has been referenced. Most of these other posts indicated results that
were less than their expectations. Is this a viable fix for this bug? On
Microsofts support page at
http://support.microsoft.com/default.aspx?scid=kb;en-us;830820 they indicate
that this fix will be incorporated into the next service pack but I have not
found any indication of when that will be released. Does anyone have any
ideas? Thanks!!
 
L

Larry

Gary -
Those who posted the issues regarding this hotfix indicated they still had lingering problems with this 'submitted message' after they had used the patch. That coupled with Microsoft's recommendation of waiting for the next service pack release made me wonder two things: Are they revising the patch from a Beta version and when will the service pack be released? Thanks ...

- Larry

----- Gary L. Chefetz (MVP) wrote: -----

Larry:

It fixes the problem. What expectations were you referring to?
 
G

Gary L. Chefetz \(MVP\)

I guess the complaints didn't register with me. I guess you'll need to
decide if you can continue without the patch and wait for SP1. Of course,
you'll then be stuck wondering whether to apply the post SP1 hotfixes as
they arrive or wait for SP2

--

Gary L. Chefetz, MVP
"We wrote the book on Project Server
http://www.msprojectexperts

-
Larry said:
Gary -
Those who posted the issues regarding this hotfix indicated they still
had lingering problems with this 'submitted message' after they had used the
patch. That coupled with Microsoft's recommendation of waiting for the next
service pack release made me wonder two things: Are they revising the patch
from a Beta version and when will the service pack be released? Thanks ...
 