"Unsubmitted Timesheets" message remains after rescheduling work

E

Eren Ersonmez

We see in PWA that some resources' timesheets are unsubmitted, when they
actually have no work scheduled for that time period.

I posted a question earlier on how to remove the "unsubmitted timesheets"
warnings, and a good solution that was offered was to "reschedule work" to a
future period. This worked in some cases. However, in some cases, we
rescheduled the resource's work to a future period(so the resource has no
work for that time period, for any projects), and PWA still shows that
resources timesheet for that period as "unsubmitted."

Any ideas why this might happen? I would appreciate your thoughts.

I don't know if this has anything to do with this issue but here's a detail:
I looked up which assignment PWA is expecting actual work to be submitted
for, and then open the resource usage view in Prj. Proffesional to see that
assignment. It has "0h" in the work field. Normally, I can click a cell and
hit 'Delete', so the cell would be empty. But in this case, I cannot get rid
of "0h" in that cell.


-Eren Ersonmez
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top