Unsubmitted timesheets

R

RickD

Resource managers are receiving "unsubmitted timesheet" notifications for
resources that are not thiers. i.e. their RBS is completely different from
the resources wwith missing timesheets. Any ideas why?
 
R

RickD

I guess the title is old, boring stuff!!

I located the issue for those interested. The Resource Manager Category had
too many resource permissions, allowing them to "see" resources on projects
they manage.
 
S

Sara - EPM

Rick,

What did you turn off, specifically? We have not been using Resc Manager
Category...we've combined the Resc and Project manager roles.

I'd like my project managers to only see resources in their RBS for
unsubmitted timesheets.

Thanks,

Sara
 
R

RickD

Sorry Sara; after posting my 2nd note I assumed there was no interest and
didn't re-check the post.

In the My direct Reports Category I unchecked "....view information for all
resources they manage".
 