Hello,
Can anyone describe the full criteria being used for the unsubmitted
timesheet filter on PWA in Project Server 2003? To my knowledge, it
will use the following critieria:
* Limit timesheet listings to those timesheets for which either Update
all or Update selected row buttons have not been used.
* Limit timesheets listings to those timesheets for which no actual
time has been entered against planned tasks (even if an Update button
has been used).
I believe this cannot be the full logic of the filter because I'm
seeing tasks for which line items are marked as accepted (so they had
to have been submitted to the PM) and no assigned tasks with zero,
showing up in this filter. Any thoughts as to why?
Thanks so much,
Wendy
Can anyone describe the full criteria being used for the unsubmitted
timesheet filter on PWA in Project Server 2003? To my knowledge, it
will use the following critieria:
* Limit timesheet listings to those timesheets for which either Update
all or Update selected row buttons have not been used.
* Limit timesheets listings to those timesheets for which no actual
time has been entered against planned tasks (even if an Update button
has been used).
I believe this cannot be the full logic of the filter because I'm
seeing tasks for which line items are marked as accepted (so they had
to have been submitted to the PM) and no assigned tasks with zero,
showing up in this filter. Any thoughts as to why?
Thanks so much,
Wendy