D
david7
Hi,
I have a project on which task type is set to "Fix Units" (effort-driven
checkbox unchecked) and on which a baseline has been saved before actual work
entries through project web access.
My problem is that the the "Work" of several tasks have been increased and
is now bigger than their "Baseline Work" whereas, their "Actual Works" have
not reached their "baseline works".
The result is that the calculated "Remaining Work" of these tasks is
becoming unaccurate.
My assumptions were:
- as long as "Actual Work" < "Baseline Work" then, "work" = "Baseline work",
- and if "Actual Work" > "Baseline Work" then, "Work" = "Actual Work".
What should I do to fix this problem?
Thanks,
I have a project on which task type is set to "Fix Units" (effort-driven
checkbox unchecked) and on which a baseline has been saved before actual work
entries through project web access.
My problem is that the the "Work" of several tasks have been increased and
is now bigger than their "Baseline Work" whereas, their "Actual Works" have
not reached their "baseline works".
The result is that the calculated "Remaining Work" of these tasks is
becoming unaccurate.
My assumptions were:
- as long as "Actual Work" < "Baseline Work" then, "work" = "Baseline work",
- and if "Actual Work" > "Baseline Work" then, "Work" = "Actual Work".
What should I do to fix this problem?
Thanks,