I am updating resource information for my enterprise resource pool (PS2007)
in Pro using the import wizard. All the information is updated correctly
EXCEPT for the base calendar. As our resources are in 4 offices, there are 4
base calendars, but after the import these all stay as Standard.
Any ideas why or what I can do to fix this?
TIA
Jen