Update a baseline on a single line item

A

Adambe

Is it possible to update a baseline on a single line item if I need to adjust
something from an error? Or do I have to delete the line and re-enter it?
 
D

Dale Howard [MVP]

Adambe --

Select the task in question and then click Tools - Tracking - Save Baseline.
In the Save Baseline dialog, choose the Selected Tasks item and click the OK
button. When prompted to ovewrite the Baseline, click the Yes button. Hope
this helps.
 
A

Adambe

Excellent. Thanks!!!!

Dale Howard said:
Adambe --

Select the task in question and then click Tools - Tracking - Save Baseline.
In the Save Baseline dialog, choose the Selected Tasks item and click the OK
button. When prompted to ovewrite the Baseline, click the Yes button. Hope
this helps.
 