I'm importing from Primavera. I've set it up so the Primvavera Task Nbr is
plopped into Text1. Now I want to "reimport", but I'll have interproject ties
in the MSP project, so I can't just overwrite it. Is there a way to "update"
a project from another project using a Text field as the "key"?